Stages
| Stage | Goal | Typical quantity | Focus |
|---|---|---|---|
| Prototype | Prove function and fit | 1–10 | Speed, flexibility, design feedback |
| Pilot / pre-series | Prove process | 10–200 | Fixtures, programs, first article inspection |
| Series | Stable output | Batches as forecast | Capability, cost, logistics |
What changes between stages
- Workholding moves from vices and generic clamps to dedicated fixtures.
- Programs are optimised for cycle time once the design is frozen.
- Material may change from plate or bar to near-net castings or forgings for volume — casting capabilities in our network can help here.
- Inspection shifts from full measurement of each part to sampling plans and SPC on critical characteristics.
Approval
For series supply we agree the approval package: first article inspection report, material certificates, process flow, and — where required — capability studies or PPAP elements. Changes after approval follow a controlled change process.
Planning tips
- Freeze critical interfaces early, iterate on non-critical features.
- Mark critical-to-function characteristics on the drawing.
- Share expected annual volumes so we can plan fixtures and material.
- Agree packaging and labelling before the first series shipment.